Concrete Patio Calculator
Estimate how many cubic yards of concrete, bags of mix, and gravel base you need for your patio slab — plus an approximate cost.
Concrete Patio Visual Guide: Layers, Measurements & Specs
Illustrated diagrams showing how a concrete patio is built — from the gravel base to control joints — plus how to measure your patio for the calculator above.
1. Concrete Patio Cross-Section
A durable patio is more than a slab. Each layer below has a job — support, drainage, or crack control.
At 4 in thick, every 100 sq ft needs 1.23 yd³ of concrete — about 56 × 80-lb bags (before waste).
- 1Concrete slab — 3,000–4,000 PSI mix; use air-entrained concrete in freeze-thaw states.
- 2Rebar or wire mesh — #3 rebar on an 18–24 in grid or 6×6 welded wire, set on chairs at mid-depth.
- 3Vapor barrier (optional) — 6-mil poly; mostly used near or under living spaces.
- 4Gravel base — about 4 in of compacted crushed stone for drainage and support.
- 5Subgrade — undisturbed or well-compacted soil with sod and topsoil removed.
- 6Isolation joint — ½ in expansion strip where the slab meets the house, steps or posts.
- 7Forms & stakes — lumber edge forms staked every 3–4 ft, removed after the concrete sets.
2. How to Measure Your Patio
Measure in feet and inches, then find the area in square feet. Odd shapes can be split into simple ones.
Rectangle / Square
L × W12 ft × 10 ft = 120 sq ftCircle
3.1416 × (D ÷ 2)²12 ft diameter ≈ 113.1 sq ftTriangle
B × H ÷ 212 ft × 10 ft ÷ 2 = 60 sq ftL-Shape
Area A + Area BSplit into 2 rectangles that don’t overlap3. Patio Thickness Guide
4 inches is the standard for a residential patio. Go thicker where heavy loads sit on the slab.
| Thickness | Best for | Per 100 sq ft |
|---|---|---|
| 3.5 in | Light foot traffic, garden paths | 1.08 yd³ · 49 bags* |
| 4 in | Standard patio, grills, furniture | 1.23 yd³ · 56 bags* |
| 5 in | Hot tubs, outdoor kitchens, fire pits | 1.54 yd³ · 70 bags* |
| 6 in | Vehicles, RV or boat parking | 1.85 yd³ · 84 bags* |
*80-lb bags, before waste. For a hot tub, always follow the manufacturer’s slab spec.
4. How Many Bags Make 1 Cubic Yard?
One cubic yard equals 27 cubic feet. Here’s how many premixed bags it takes to fill it:
0.60 cu ft each
0.45 cu ft each
0.30 cu ft each
Rule of thumb: under ~1 yd³, bags are practical. Above ~2–3 yd³, ready-mix delivery is usually easier and gives a more uniform slab. Many suppliers charge a short-load fee on small orders.
5. Slope & Drainage
A patio must slope away from the house so rainwater never runs toward your foundation.
| Patio depth (from house) | Total drop at ⅛ in/ft | Total drop at ¼ in/ft |
|---|---|---|
| 10 ft | 1¼ in | 2½ in |
| 12 ft | 1½ in | 3 in |
| 16 ft | 2 in | 4 in |
6. Control Joint Layout
Concrete shrinks as it cures and will crack. Control joints tell it where to crack — in a straight, neat line.
- ↔Spacing: 2–3 × slab thickness, in feet. A 4 in slab → joints every 8–12 ft.
- ↓Depth: ¼ of the slab thickness (1 in deep for a 4 in slab).
- □Panel shape: keep panels close to square; long side no more than 1.5 × the short side.
- ⏱Timing: tool joints while finishing, or saw-cut within 6–18 hours of the pour.
7. Step-by-Step: Pouring a Concrete Patio
- Plan, permit & call 811Check local permit and setback rules, then call 811 at least a few business days before digging so buried utility lines are marked.
- ExcavateRemove sod and topsoil. Dig about 8 in deep for a 4 in gravel base + 4 in slab (less if the slab sits above grade).
- Build the formsA 2×4 is only 3.5 in tall — use 2×4s for 3.5 in slabs and 2×6s for 4–6 in slabs. Stake every 3–4 ft and set the slope.
- Add & compact gravelSpread crushed stone in 2–3 in lifts and compact each lift with a plate compactor.
- Place reinforcementSet rebar or wire mesh on chairs so it sits in the middle of the slab — not on the gravel.
- Pour, screed & floatPour in sections, screed level with the forms, then bull float to push down the stones and bring up the cream.
- Edge, joint & finishRound the edges with an edger, cut control joints, and apply a broom finish for slip resistance.
- CureKeep the slab moist for about 7 days (sprinkle, cover with plastic, or spray a curing compound).
8. Curing Timeline: When Can You Use It?
- Day 0Pour & finish. Keep people, pets and rain off.
- 24–48 hrsOK for light foot traffic.
- 7 daysAbout 70% strength. Patio furniture and grills OK.
- 28 daysDesign strength reached. Safe for heavy loads like a hot tub; apply sealer now if desired.
Times assume roughly 50–90°F weather. Cold slows curing; avoid pouring if a freeze is expected within 24–48 hours unless the slab is protected.
Quick Reference: Concrete Patio Specs
- Standard thickness
- 4 in
- Gravel base
- 4 in, compacted
- Concrete strength
- 3,000–4,000 PSI
- Reinforcement
- #3 rebar 18–24 in O.C. or 6×6 wire mesh
- Slope
- ⅛–¼ in per ft, away from house
- Control joints
- Every 8–12 ft (4 in slab), ¼ depth
- Waste allowance
- 5–10%
- Full strength
- 28 days
General guidance for typical US residential patios. Local building codes, soil conditions and climate may require different specs.