Concrete Quantity Calculator
Estimate cubic yards, premix bags and cost for slabs, footings, columns and stairs.
Concrete needed
Calculator is loading… If results don’t appear, please refresh the page.
Enter your dimensions and press Calculate to see the result.
- 0cubic feet
- 0cubic meters
- 0yd³ to order
- 080 lb bags
- 060 lb bags
- 040 lb bags
“To order” is rounded up to the nearest ¼ yd³, as most ready-mix suppliers require. Bag yields: 80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³, 40 lb ≈ 0.30 ft³.
How is concrete volume calculated?
- Slab / footing: Length × Width × Thickness (in feet) ÷ 27 = cubic yards.
- Column: π × (Diameter ÷ 2)² × Height ÷ 27.
- Stairs: Width × Rise × Run × n(n+1)/2, plus any top landing.
- For jobs under ~1 yd³, bagged mix is usually cheaper; larger pours are better suited to ready-mix delivery.
Concrete Quantity Guide: How Much Concrete Do You Need?
Concrete is sold by the cubic yard in the US. These diagrams show how to measure any slab, footing, column or stair, turn it into cubic yards, and decide between premix bags and a ready-mix truck.
1. The basic formula (slabs, patios, driveways)
Every rectangular pour is a box. Multiply its three dimensions in feet to get cubic feet, then divide by 27 to get cubic yards.
Cubic yards = Length × Width × Thickness ÷ 27All three measurements in feet. Thickness in inches ÷ 12 = feet.
- 4 in ÷ 12 = 0.333 ft
- 12 × 10 × 0.333 = 40 ft³
- 40 ÷ 27 = 1.48 yd³
- +10% waste = 1.63 yd³ → order 1.75 yd³
2. Why divide by 27?
A cubic yard is a cube 3 ft long, 3 ft wide and 3 ft tall. Stack the one-foot cubes inside it and you get 3 × 3 × 3 = 27 cubic feet.
Thickness is the measurement people most often get wrong. Use this table to convert inches to feet before you multiply:
| Thickness | In feet | Common use |
|---|---|---|
| 3 in | 0.25 ft | Overlay, thin topping |
| 4 in | 0.333 ft | Patio, sidewalk, shed |
| 5 in | 0.417 ft | Driveway |
| 6 in | 0.5 ft | Heavy driveway, garage |
| 8 in | 0.667 ft | Footings, heavy pads |
3. Footings
A continuous footing is a long, narrow box. Measure the total length of footing around the structure, then use its width and depth.
Cubic yards = Total length × Width × Depth ÷ 27Footing size is set by your local building code — check it before you pour.
- 20 in = 1.667 ft · 12 in = 1 ft
- 40 × 1.667 × 1 = 66.67 ft³
- 66.67 ÷ 27 = 2.47 yd³
4. Columns, Sonotubes & post holes
Round forms are cylinders. Halve the diameter to get the radius, square it, multiply by π (3.1416) and the height.
Cubic yards = 3.1416 × (Diameter ÷ 2)² × Height ÷ 27Diameter and height in feet. Multiply by the number of holes.
- Radius = 6 in = 0.5 ft
- 3.1416 × 0.5² × 4 = 3.14 ft³
- 3.14 ÷ 27 = 0.12 yd³ → about 6 bags of 80 lb mix
5. Concrete stairs
Solid steps stack up like blocks: the first step is 1 block tall, the second 2, and so on. For n steps that’s 1 + 2 + … + n = n(n+1) ÷ 2 blocks.
Cubic yards = Width × Rise × Run × n(n+1)÷2 ÷ 27Add any top landing separately: Width × Landing depth × Total height.
- Blocks = 4 × 5 ÷ 2 = 10
- 4 × 0.583 × 0.917 × 10 = 21.39 ft³
- 21.39 ÷ 27 = 0.79 yd³
6. Premix bags vs. ready-mix truck
Bagged concrete is labeled by weight, but what matters is how much volume each bag yields once mixed. Divide your cubic feet by the bag yield and round up.
Bags = Cubic feet ÷ Bag yield80 lb ≈ 0.60 ft³ · 60 lb ≈ 0.45 ft³ · 40 lb ≈ 0.30 ft³
- Under about 1 yd³: bags are usually practical (post holes, small pads, steps).
- Over about 1 yd³: ready-mix delivery saves a lot of mixing labor. Many suppliers sell in ¼ yd³ steps and may add a fee for small loads.
- Check the yield printed on your brand’s bag — it can vary slightly.
7. Quick thickness chart & area estimator
Each extra inch of thickness adds about 0.31 yd³ per 100 sq ft. Enter your area to see how much you need at each thickness.
| Thickness | yd³ needed | Order (yd³) | 80 lb bags |
|---|---|---|---|
| 3 in | 1.02 | 1.25 | 46 |
| 4 in | 1.36 | 1.50 | 62 |
| 5 in | 1.70 | 1.75 | 77 |
| 6 in | 2.04 | 2.25 | 92 |
| 8 in | 2.72 | 2.75 | 123 |
“yd³ needed” includes waste. Order is rounded up to the nearest ¼ yd³.
8. Step-by-step checklist
- MeasureLength, width and thickness (or diameter and height). Measure thickness in several spots.
- Convert to feetInches ÷ 12. Yards × 3.
- MultiplyL × W × T for boxes, π × r² × H for round forms.
- Divide by 27Cubic feet ÷ 27 = cubic yards.
- Add waste5–10% for spillage, form bulge and uneven base.
- Round upTo the nearest ¼ yd³ for ready-mix, or whole bags for premix.
9. Common mistakes to avoid
- Multiplying inches by feet. 10 × 10 × 4 = 400 is wrong — use 10 × 10 × 0.333 = 33.3 ft³.
- Forgetting the ÷ 27. 33.3 is cubic feet; it’s only 1.23 cubic yards.
- Ordering the exact amount. Running short mid-pour creates a cold joint. Always add waste.
- Ignoring an uneven base. A sub-base that dips by just ½ in across a slab adds noticeable volume.
- Treating bag weight as volume. An 80 lb bag makes only about 0.6 ft³ — it takes 45 of them for one yard.
Concrete Quantity Calculator
Find out how many yards to order, how many bags to buy, and what your pour will cost.
This concrete quantity calculator turns your project measurements into a clear shopping list: cubic yards to order from a ready-mix supplier, premix bags to buy, and an estimated cost. Getting the number right matters. If you run short in the middle of a pour, you can end up with a weak cold joint. If you order too much, you pay for concrete you have to dispose of.
How to Use the Concrete Quantity Calculator
- Pick your project type. Choose Slab / Wall, Footing, Column / Hole, or Stairs.
- Enter your dimensions.
- Slab / Wall: Length (ft), Width (ft), Thickness (in), and Quantity (pcs). Use Quantity for identical pieces, such as three matching pads.
- Footing: the length, width, and depth of a continuous (strip) footing.
- Column / Hole: the diameter and depth of a round column, sonotube, or post hole.
- Stairs: the number of steps, the rise and run of each step, and the stair width.
- Switch units if needed. Each field has a unit selector, so you can enter inches or feet without converting by hand.
- Set your waste / overage. The default is 10%. Use 5–10% for most jobs, and go higher for tricky pours.
- Add a ready-mix price (optional). Enter your local supplier’s price per cubic yard to see an estimated cost.
- Press Calculate and read your results.
- Concrete needed shows the volume in cubic yards and cubic feet, including waste.
- To order rounds that up to the nearest ¼ yd³. Give this number to your ready-mix supplier.
- Bags shows how many 40 lb, 60 lb, or 80 lb premix bags you need.
- Estimated cost appears when you enter a price.
How Concrete Quantity Is Calculated
Every mode works out the volume in cubic feet first. The formulas are:
- Slab / wall: Length × Width × (Thickness in ÷ 12)
- Footing: Length × Width × Depth
- Column / hole: π × (Diameter ÷ 2)² × Depth
- Stairs: Treat each step as a solid block that sits on the ground. The bottom step is one rise tall, the second is two rises tall, and so on. Each block is one run deep and as wide as the stairs. Add the blocks together. If you have a landing, calculate it as a slab at full stair height and add it.
Next, the calculator converts and pads the number:
- Convert to cubic yards: ft³ ÷ 27 = yd³ (1 yd³ ≈ 0.76 m³).
- Add waste: yd³ × (1 + waste %).
- Round up: to the next ¼ yd³ for the “To order” amount.
Worked Examples by Project
Example 1: 10 ft × 10 ft Patio Slab, 4 in Thick
- Volume: 10 × 10 × (4 ÷ 12) = 33.33 ft³
- Cubic yards: 33.33 ÷ 27 = 1.23 yd³
- With 10% waste: 1.23 × 1.10 = 1.36 yd³ (36.67 ft³, about 1.04 m³)
- To order: round up to 1.5 yd³
- 80 lb bags: 36.67 ÷ 0.60 = 61.1, so buy 62 bags
At 62 bags, this job sits right on the line between bags and ready-mix. Most people order the truck here.
Example 2: Continuous Footing, 40 ft × 24 in × 12 in
This is a typical strip footing for a garage wall or small addition.
- Convert to feet: 24 in = 2 ft, 12 in = 1 ft
- Volume: 40 × 2 × 1 = 80 ft³
- Cubic yards: 80 ÷ 27 = 2.96 yd³
- With 10% waste: 2.96 × 1.10 = 3.26 yd³ (88 ft³)
- To order: 3.5 yd³
- 80 lb bags: 88 ÷ 0.60 = 146.7, so 147 bags
Nobody wants to hand-mix 147 bags. Order ready-mix.
Sample cost estimate: Say your supplier quotes $165 per yd³. You pay for what you order, so 3.5 × $165 = $577.50 for the concrete. This price is only an example. Delivery fees, short-load fees, and pump rental are extra, and prices vary widely by region.
Before you pour, check your local code. Footings must sit below the frost line, and the depth varies a lot across the US.
Example 3: Ten Fence Post Holes, 10 in Diameter × 36 in Deep
- Radius: 10 ÷ 2 = 5 in = 0.417 ft
- One hole: π × 0.417² × 3 = 1.64 ft³
- Ten holes: 1.64 × 10 = 16.36 ft³ (0.61 yd³)
- With 10% waste: 16.36 × 1.10 = 18.0 ft³ (0.67 yd³)
- To order: 0.75 yd³, but you probably shouldn’t order a truck
- 80 lb bags: 18.0 ÷ 0.60 = 30 bags (3 per hole)
Here’s why bags win for post holes. The total is well under 1 yd³, so a ready-mix order would likely trigger a short-load fee. The holes are spread along a fence line where a truck can’t reach. You also set posts one at a time, and fast-setting concrete lets you do that without a mixer.
The post itself takes up a little space. Keep that as extra cushion, since post holes almost always end up wider than planned. Note that fast-setting mixes yield differently than standard mix, so check the bag label.
Example 4: Concrete Steps, 4 Steps, 7 in Rise, 11 in Run, 4 ft Wide
Each block is 11 in deep and 48 in wide. Heights are 7, 14, 21, and 28 in.
- One “unit” block: (7 × 11 × 48) ÷ 1,728 = 2.14 ft³
- Stacked steps: 1 + 2 + 3 + 4 = 10 units, so 2.14 × 10 = 21.39 ft³ (0.79 yd³)
- With 15% waste for stair forms: 21.39 × 1.15 = 24.60 ft³ (0.91 yd³)
- To order: 1.0 yd³
- 80 lb bags: 24.60 ÷ 0.60 = 41.0, so 41 bags
A common mistake is forgetting the top landing. A landing adds a full-height slab, which can double the total on a short set of steps.
How Many Bags of Concrete Do I Need?
Here’s how many premix bags make up one cubic yard (27 ft³), based on the calculator’s yields:
| Bag size | Yield per bag | Bags per 1 yd³ | Bags per ½ yd³ | Total weight per yd³ |
|---|---|---|---|---|
| 40 lb | 0.30 ft³ | 90 | 45 | 3,600 lb |
| 60 lb | 0.45 ft³ | 60 | 30 | 3,600 lb |
| 80 lb | 0.60 ft³ | 45 | 23 | 3,600 lb |
A few practical notes:
- Every yard is close to 2 tons of material. Plan how you’ll get it home. That much weight can overload a pickup or a small trailer.
- 80 lb bags are the most efficient but the hardest to handle. 60 lb or 40 lb bags make sense if you’re working alone or carrying bags a long way.
- Mixing takes time. Expect a few minutes per batch in a drum mixer, plus loading and wheelbarrow trips. Large bag jobs need a crew so early batches don’t set before you finish.
- Yields vary by product. Quikrete, Sakrete, and other brands print the yield on each bag. If your bag says something different, trust the bag.
Bags vs. Ready-Mix: When to Use Each
| Factor | Premix bags | Ready-mix truck |
|---|---|---|
| Best project size | Under about 1 yd³: post holes, small pads, repairs | About 1 yd³ and up: patios, driveways, footings |
| Labor | High. You mix every batch by hand or mixer. | Low. Concrete arrives mixed and ready to place. |
| Cost | Cheap for small jobs, expensive per yard at scale | Lower cost per yard, but fees hit small orders hard |
| Access | Goes anywhere you can push a wheelbarrow | Needs truck access, or a pump for backyards |
| Consistency | Varies batch to batch | Uniform mix from the batch plant at a set PSI |
Watch for minimum orders and short-load fees. Many suppliers charge extra for loads below a set size. Since a typical truck holds 8–10 yd³, a 1 yd³ order costs them nearly as much to deliver as a full load. Ask about these fees when you call for a quote.
How to Estimate Concrete Cost
Your total budget depends on more than the price per yard. The main cost drivers are:
- Ready-mix price per yd³: set by mix strength (often 2,500–4,000 PSI) and any additives
- Delivery fee: often charged per trip
- Short-load fee: for orders below the supplier’s minimum
- Wait time: charged if the truck sits too long while you place concrete
- Concrete pump rental: needed when the truck can’t reach the pour
- Bags: your bag count × local shelf price
- Formwork, rebar, wire mesh, and gravel base: materials that come before the pour
- Labor: if you hire finishers
Prices change by region and season, so get two or three local quotes. Enter the per-yard price in the calculator for a quick concrete cost estimate.
Pro tip: To compare bags against ready-mix, multiply your local 80 lb bag price by 45. That gives you the cost per yard in bags.
Why You Should Round Up and Add Waste
The ¼ yd³ rule. Most ready-mix suppliers sell in quarter-yard increments. If your math says 1.36 yd³, you can’t order exactly that, so the calculator rounds up to 1.5 yd³.
The 5–10% waste guideline. Real job sites never match the drawing. Concrete spills, forms bow out, and the subgrade has low spots. A 4 in slab poured over a base that dips to 4½ in uses about 12% more concrete than planned.
When to go higher (10–15%):
- Uneven or soft subgrade that you couldn’t fully level
- Complex forms with curves, steps, or many corners
- Concrete stairs, where forms flex and every step edge adds spillage
- Hand mixing, where some concrete stays in the mixer and the wheelbarrow
- Over-excavation, such as post holes or trenches dug wider than planned
Running short costs far more than a little extra. A second truck means another delivery fee, and the delay can leave a visible seam in your slab.
Tips for Ordering the Right Amount
- Measure in several spots. Check thickness at the corners and the center. Use your deepest common measurement, not the shallowest.
- Check form depth with a string line. Stretch a string across the top of the forms and measure down to the base every few feet.
- Compact the base first. A soft gravel base settles under wet concrete and swallows extra volume. Compact it well before you set your final numbers.
- Keep a few bags on hand. Even with a truck coming, five or six 80 lb bags can fill a small gap or finish a post hole.
- Confirm truck access. Ask how far the chute reaches. If it can’t get close enough, book a pump or line up extra wheelbarrows and helpers.
- Schedule smart. Book the truck early in the day, avoid extreme heat, and have your crew, tools, and formwork ready before it arrives.
- Reconfirm the day before. Call your supplier to confirm the yardage, mix, and delivery time.
FAQs
How much concrete do I need for a 10×10 slab?
You need about 1.23 cubic yards for a 10 × 10 ft slab at 4 inches thick. With 10% waste, that’s 1.36 yd³, so order 1.5 yd³ or buy 62 80 lb bags. A 6-inch driveway-grade slab needs about 2.04 yd³ with waste, so order 2.25 yd³.
How many 80 lb bags of concrete make a yard?
It takes 45 bags of 80 lb concrete to make one cubic yard. Each bag yields about 0.60 cubic feet, and a yard holds 27 cubic feet. For 60 lb bags you need 60, and for 40 lb bags you need 90. Always check the yield printed on your specific brand.
How many bags of concrete do I need per fence post?
Most fence posts need two to three 80 lb bags each. A 10-inch-wide, 36-inch-deep hole holds about 1.64 cubic feet, which is about three bags once you add waste. Wider or deeper holes need more. Enter your hole size in the Column / Hole mode for an exact count.
Is it cheaper to buy bags or ready-mix concrete?
Bags are usually cheaper for jobs under about one cubic yard. Above that, ready-mix typically costs less per yard and saves hours of labor. Short-load fees and delivery charges can change the math, so compare a local ready-mix quote against your bag count multiplied by the local bag price.
How much extra concrete should I order?
Order 5–10% extra for most slabs, walls, and footings. Go up to 10–15% for stairs, uneven ground, complex forms, or hand mixing. Then round up to the nearest quarter yard for ready-mix. Running short mid-pour costs more than a small surplus, so lean toward the higher end.
How thick should a concrete slab be?
A patio or walkway slab is typically 4 inches thick. A driveway is usually 5–6 inches, especially if it carries heavy trucks. Thickness has a big effect on volume, since a 6-inch slab uses 50% more concrete than a 4-inch slab. Always follow your local code and any engineered plans.
What is a short-load fee?
A short-load fee is an extra charge for ready-mix orders below the supplier’s minimum load size. The truck, driver, and fuel cost nearly the same whether they deliver one yard or ten. The fee amount and minimum vary by supplier, so ask about both when you request a quote.
How many yards of concrete does a truck hold?
A standard ready-mix truck typically holds 8–10 cubic yards. Some suppliers also run smaller trucks for short loads. If your project needs more than one full truck, schedule the deliveries close together so the second load arrives before the first starts to set.
Get Your Order Right the First Time
A good concrete quantity calculator saves you from the two costly mistakes: running short and over-ordering. Measure carefully, choose the right project mode, add realistic waste, and use the “To order” and bag results to buy with confidence. Then enter a local price to see your budget before the truck shows up.